February Task Force USL BoT Update
Final Paperwork on New Building: Final sign-off has moved up to Feb. 23rd, 2021 and we can then occupy the building. Warranties on all aspects
Final Paperwork on New Building: Final sign-off has moved up to Feb. 23rd, 2021 and we can then occupy the building. Warranties on all aspects
New Building Progress Report – November Work Begins! First serious work began this month with a complete cleaning of the exterior building via pressure washing.
New Building Progress Report September-October Lots of good news this month! After reviewing the lowest bids, the USL Board of Trustees awarded the New Library
SHKS completed their responses to the USL Comment Sheet concerning the final package of work. SHKS also sent their COVID-19 Phase 2 Construction Safety Guidance
As you may know, in recent months The Board of Trustees has gained some new faces and thanked others for their hard work and service