- Final Paperwork on New Building:
- Final sign-off has moved up to Feb. 23rd, 2021 and we can then occupy the building.
- Warranties on all aspects of the building start February 26th, 2021
- We are free to move material in now (as long as any dent, scratch, etc. damage is on USL’s nickel)
- Moving the Technology to the New Building:
- Loly is checking with K-20 to ensure the new building is “hot”
- Loly and I can move all equipment with help from Nathaniel Martin (high school IT)
- Nathaniel has volunteered to do a pre-walkthrough as well as help us disengage all equipment from the current site carefully and correctly. He will also help with the install at the new building as needed
- Wireless antenna can remain at the old building – pending approval: Claudia & Joy
- Wireless will also be available in the new building
- Shelving:
- Shelving framework has been laid out in place
- Installation next Monday & Tuesday
- Library staff will decide shelving heights, types, etc. on Monday
- Front Counter:
- It is set up and will be secured to the floor on Monday
- Signage:
- Only bid so far is too expensive, $1400 for seven 30” Letters
- Can order those letters online for $700 or buy stencils at about $350
- I’ve put out an inquiry to Don Smith, muralist and artist, to see if he is interested
- Keys:
- Exterior doors rekeyed to one master key
- I’ve tagged and hung all keys in a key box for the staff to distribute as needed
- Storage:
- Cleaned up and room to move
- All Friends materials are now in one place
- Next Month:
- The Task Force will end its work as it will have met its goal of “coordinating the new library building”
- A final Task Force Report covering 2014 to 2020 will be available for reading online